1a
Sme Calculator
2 marks

A toy car is released from rest and rolls down a slope, as shown.

q11-wph11-01-oct-2021-edexcel-int-as-and-a-level-phy

mass of car = 0.160 kg
speed of car at bottom of slope = 2.6 m s–1.

Calculate the increase in kinetic energy of the car as it accelerates down the slope.






Increase in kinetic energy = .......................................
1b
Sme Calculator
2 marks

As the car accelerates down the slope, the work done against frictional forces is 0.26 J.

Calculate the vertical displacement of the car.






Vertical displacement of car = ...................................

Did this page help you?

2a
Sme Calculator
2 marks

The diagram shows a lift system for moving people up and down a tall building. There is a counterweight to balance the weight of the lift. An electric motor is used to raise and lower the lift.

q12-wph11-01-jan-2022-edexcel-int-as-a-level-phy

Explain how the counterweight affects the amount of work required from the electric motor to raise the lift.

2b
Sme Calculator
4 marks
The electric motor raises the lift through a height of 40.0 m in a time of 30.0 s.
 

Show that the output power of the electric motor is about 12 kW. 

   total mass of lift and people = 2250 kg
   mass of counterweight = 1300 kg

2c
Sme Calculator
2 marks

The electric motor dissipates energy to the surroundings at a rate of 3600 W.

Determine the efficiency of the electric motor.




Efficiency = .............................

Did this page help you?

3a
Sme Calculator
2 marks

The diagram shows a system used to move a stone block up a ramp. A team of people uses a rope to pull the block at a constant speed.

q18-wph11-01-oct-2021-edexcel-int-as-and-a-level-phy

height of ramp = 4.35 m
angle of ramp to horizontal = 6.0°
mass of block = 2.10 × 103 kg
speed of block up ramp = 0.450 m s–1
total power of team = 6.25 kW

Show that the total force that the team exerts on the block is about 14 kN.

3b
Sme Calculator
3 marks
Determine the total work done by the team.






Total work done = ...........................................

3c
Sme Calculator
2 marks
Show that the useful work done on the block is about 90 kJ.
3d
Sme Calculator
2 marks

Determine the efficiency of the system.





Efficiency = ........................................

Did this page help you?