Resource Histograms (Edexcel A Level Further Maths) : Revision Note

Paul

Author

Paul

Last updated

Constructing a Resource Histogram

What is a resource histogram?

  • A resource histogram is a graphical way of showing the number of resources needed during each time unit (e.g. day) of a project

  •  A 'resource' usually refers to a person (called a worker) but could refer to

    • a team of workers (e.g.  bricklayers, roofers, painters)

    • a machine (e.g.  cement mixer)  

  • The number of workers needed will vary as a project progresses and will be determined by

    • the activities that need to happen at a particular time

    • the number of workers needed per activity

  • A resource histogram shows at a glance the maximum (and minimum) number of workers/resources needed for a project

  • Resource histograms can be used to help minimise the number of workers at any particular time during a project

What assumptions are made in drawing a resource histogram?

  • In the first instance, there are three main assumptions used in order to construct a resource histogram

    • Each activity begins at its earliest event time

    • A worker/resource can only carry out one activity at a time

    • Once an activity has begun, it must be completed in one go e.g.  If an activity C, say, of duration 5 days, starts on day 7, it has to take place on days 7, 8, 9, 10, 11 It cannot be done on days 7, 8, 12, 13, 14  for example

  • Once a resource histogram is constructed, the assumptions can be reconsidered

    • This may be so that the number of workers/resources required at any given time is minimised

      • This process is called resource levelling and is covered in the next revision note

How do I draw a resource histogram?

  • The horizontal axis is used for time

    • However units of time are treated as discrete data

    • So "day 1" would be labelled underneath the first column 

  • The vertical axis is used for the number of resources (number of workers)

  • For each unit of time

    • a box per worker is drawn with a label of the activity that worker is doing

    • multiple boxes are 'stacked' on top of each other

      • critical activities are at the bottom of the stack

      • other activities appear in alphabetical order

  • Each activity commences at its earliest event time

Worked Example

The Gantt chart for a project is shown below, with the duration of each activity measured in days.

ONRUwhbY_reshist-we-qu-gantt

The table below shows the number of workers required for each activity.

Activity

No. of workers

A

2

B

1

C

3

D

2

E

1

F

2

G

3

H

1

I

2

J

2

Construct a resource histogram for the project, assuming that each activity starts at the earliest possible time.

Activity A requires 2 workers and lasts for 5 days

reshist-we-1

Add the rest of the critical activities with their number of workers

reshist-we-2

Other activities can be added in order
Activity B is straightforward but activity D gets 'bumped' up for days 6 and 7 days due to activity C requiring 3 workers (whilst activity A only needed 2 workers)

reshist-we-3

Add the other activities carefully, one at a time, considering where any are 'bumped' up or down

reshist-we-4

It is always worth double checking - especially any 'bumped' activities - and check the minimum duration time (23 days)

reshist-we-5-final

You've read 0 of your 5 free revision notes this week

Sign up now. It’s free!

Join the 100,000+ Students that ❤️ Save My Exams

the (exam) results speak for themselves:

Did this page help you?

Paul

Author: Paul

Expertise: Maths Content Creator (Previous)

Paul has taught mathematics for 20 years and has been an examiner for Edexcel for over a decade. GCSE, A level, pure, mechanics, statistics, discrete – if it’s in a Maths exam, Paul will know about it. Paul is a passionate fan of clear and colourful notes with fascinating diagrams.